Pemberton Area Flood Protection Works 2004/05
Project Introduction:
The Pemberton Valley area experienced extensive
flooding during a high rainfall event in October 2003. Rainfall
records were set in the Squamish – Pemberton corridor with
over 369 mm of rain over a four day period. The high rainfall/water
event caused extensive erosion of stream channel banks, dykes and
bridges in the Pemberton area. Cascade Environmental Resource Group
Ltd. was retained to provide permitting and environmental monitoring
services for restoration works for the Lil’wat First Nations
(Mt. Currie), the Lower Stl’atl’imx First Nations (between
Lillooet Lake and Harrison Lake), and the Pemberton Valley Dyking
District.
Problem Statement:
A high rainfall event in October 2003 caused
extensive erosion damage to road, bridge and property in the Pemberton
area.
Solution Description:
In response to the damage and erosion caused
by the high rainfall/water event in October 2003, a recovery plan
was prepared for the BC Provincial Emergency Program. The plan identified
many sites in the Pemberton area that were in need of immediate
restoration. The sites included the repair of extensive erosion
to channel banks, dykes and bridges; gravel extraction; as well
as bridge and culvert replacements. A total of 17 projects were
completed by Cascade Environmental Resource Group Ltd. over a two
year period (2004/05).
Bank and dyke protection works entailed
the installation of 800 mm riprap and filter gravel. All attempts
were made to place the rock around vegetation to preserve critical
riparian habitat. In projects along rivers with critical salmonid
habitat (i.e. Birkenhead River) root wads were interlocked within
the riprap. Bridge protection works also included the installation
of riprap and filter gravel. Other restoration works included the
replacement of blocked or damage culverts and the replacement of
a damaged bridge at Rogers Creek. Extensive gravel extraction works
were completed at Miller Creek (northwest of the Village of Pemberton)
to remove approximately 4000 to 6000 m3 of bed material. The material
was transported downstream during a debris flood event in October
2003.
Conclusion:
Bank, dyke and bridge protection; gravel
extraction; and culvert and bridge replacement works were completed
in the Pemberton area over a two year period in response to a high
rainfall/water event in October 2003. To restore the sites to pre-flood
conditions, Cascade Environmental Resource Group Ltd. completed
the environmental monitoring and permitting for a total of 17 projects
over a two year period.

Installation of riprap and root wads along Birkenhead River
September 2004 |
|

Placement of riprap along Lillooet River near Pemberton
August 2004 |
|